Work Performed, July 31st to August 11th
·
Graded base course of gravel prior to paving
first layers of asphalt pavement
·
Paved first layer of asphalt pavement
·
Restored concrete driveways
·
Prepared for asphalt driveway restorations
·
Reinstalled mailboxes
Work Anticipated to be Performed, August 14th
to August 18th
·
Perform final testing of water main
·
Adjust manholes prior to final paving
·
Perform internal televising of sewers
·
Rough grade and install topsoil along the edge
of pavement
With the installation of the first
layers of asphalt pavement, hopefully the driving condition are much improved
by reducing the amount of dust and providing a smooth driving surface. The asphalt
driveways will be restored following the installation of the surface layer of
asphalt.
The contractor will be
working to performing several miscellaneous tasks prior to paving the final
layer of asphalt including all final testing of the underground work performed.
The contractor will be
installing and grading topsoil; however, sod will not be installed until
mid-September when the growing conditions are typically more favorable.
Hopefully a majority of the
construction work, with the exception of sod installation, will be completed in
the next 2-3 weeks.
Thanks again for all your
patience and understanding.