Friday, August 25, 2017

Asphalt Paving Completed

Work Performed, August 21st to August 25th  
·         Paved final surface layer of asphalt
·         Performed final testing of water main system

Work to be Performed
·         Asphalt driveway restoration
·         Pavement patching near Wagner Road
·         Minor repairs indentified outside the pavement
·         Final inspection with Village staff prior to project close-out.
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

Friday, August 18, 2017

Final Layer of Asphalt Surface Pavement being Scheduled

Work Performed, August 14th to 18th   
·         Started final testing of water main
·         Made repairs to water main identified during testing
·         Adjust manholes prior to final grade
·         Excavate, grade, and install topsoil in landscape area
·         Internally televising underground storm and sanitary sewers
·         General site clean-up.

Work Anticipated to be Performed, August 21st to August 25th  
·         Complete final testing of water main
·         Complete excavation, grading, and installation of topsoil in landscape areas
·         Pave final layer of asphalt

The contractor will continue to install and grade topsoil; however, sod will not be installed until mid-September when the growing conditions are typically more favorable.

Hopefully a majority of the construction work, with the exception of sod installation, will be completed in the next 1-2 weeks.

Thanks again for all your patience and understanding.

Monday, August 14, 2017

Preparing for Final Layer of Asphalt Pavement

Work Performed, July 31st to August 11th  
·         Graded base course of gravel prior to paving first layers of asphalt pavement
·         Paved first layer of asphalt pavement
·         Restored concrete driveways
·         Prepared for asphalt driveway restorations
·         Reinstalled mailboxes

Work Anticipated to be Performed, August 14th to August 18th
·         Perform final testing of water main
·         Adjust manholes prior to final paving
·         Perform internal televising of sewers
·         Rough grade and install topsoil along the edge of pavement

With the installation of the first layers of asphalt pavement, hopefully the driving condition are much improved by reducing the amount of dust and providing a smooth driving surface. The asphalt driveways will be restored following the installation of the surface layer of asphalt.

The contractor will be working to performing several miscellaneous tasks prior to paving the final layer of asphalt including all final testing of the underground work performed.

The contractor will be installing and grading topsoil; however, sod will not be installed until mid-September when the growing conditions are typically more favorable.

Hopefully a majority of the construction work, with the exception of sod installation, will be completed in the next 2-3 weeks.

 

Thanks again for all your patience and understanding.