·
Performed excavation and installation of gravel
base materials within pavement widening area.
·
Removed unstable materials under proposed
pavement widening area.
·
Removed existing asphalt pavement
·
Excavated under existing pavement and installed
new gravel base materials
Work Anticipated to be Performed, July 31st to
August 4th
·
Fine grading of aggregate base materials
·
Paving first layer of asphalt pavement
·
Rough grading of landscape restoration areas
It is anticipated the first
layer asphalt pavement will be installed next week. This is a major project
milestone because the amount of dust will be greatly reduced as well as
providing a smooth driving surface.
Thank you for all your
patience as you have been traveling along a roadway under construction for an
extended period of time.