Work Completed, May 22nd to May 26th  
·         Directional drilling of water main
·         Installation of fire hydrants and valves

Work Anticipated to be completed, May 30th to June 2nd  
·         Complete water main installation
·         Begin storm sewer installation near Wagner Road and work east