Completed water main installation across Wagner
Road
·
Completed storm sewer installation
·
Begin testing newly installed water main.
Work Anticipated to be performed, June 12th to
June 16th
·
Perform necessary testing and acquiring needed
approvals prior to placing the new water main into service
Starting the week of June 19th, the contractor will begin installing new water services to each home for connection by the homeowner at a future date. We will attempt to contact you to determine the best place for the water service to make it easiest for future connections. If you do have a preferred location, please contact us to schedule a time to meet.
Thanks again for all your patience and understanding during
construction.