Monday, June 12, 2017

Storm Sewer and Water Main Installation Completed. Testing for Water Main Started. Water Service Replacements Begin week of June 19th

Work Performed this Week, June 5th to June 9th
·         Completed water main installation across Wagner Road
·         Completed storm sewer installation
·         Begin testing newly installed water main.

Work Anticipated to be performed, June 12th to June 16th  
·         Perform necessary testing and acquiring needed approvals prior to placing the new water main into service

Starting the week of June 19th, the contractor will begin installing new water services to each home for connection by the homeowner at a future date. We will attempt to contact you to determine the best place for the water service to make it easiest for future connections. If you do have a preferred location, please contact us to schedule a time to meet.

 

Thanks again for all your patience and understanding during construction.