Friday, June 23, 2017

Water Service Installation to Begin

Work Performed, June 19th to June 23rd  
·         No work performed

Work Anticipated to be performed, June 26th to June 30th  
·         Water service installations.
·         General site clean-up in preparation for July 4th Weekend.

This week, the contractor will begin installing new water services to each home for connection by the homeowner at a future date. We will attempt to contact you to determine the best place for the water service to make it easiest for future connections. If you do have a preferred location, please contact us to schedule a time to meet.

Many of you have likely heard in the news about the potential for construction shut-downs associated without having a state budget passed by the legislature. This project is not affected by that potential shut-down since no State or Federal funds are being utilized.  This project is 100% funded by the Village of Glenview; therefore, work will continue without delay.

Thank you for all your patience as you are dealing with the inconveniences that come with living in a construction area.

Monday, June 19, 2017

Water Service Installations to Begin

Work Performed, June 12th to June 16th
·         Performed necessary testing and received approvals to place new water main into service

Work Anticipated to be performed, June 19th to June 23rd   
·         Begin water service installations

This week, the contractor will begin installing new water services to each home for connection by the homeowner at a future date. We will attempt to contact you to determine the best place for the water service to make it easiest for future connections. If you do have a preferred location, please contact us to schedule a time to meet.

 

Thanks again for all your patience and understanding during construction.

Monday, June 12, 2017

Storm Sewer and Water Main Installation Completed. Testing for Water Main Started. Water Service Replacements Begin week of June 19th

Work Performed this Week, June 5th to June 9th
·         Completed water main installation across Wagner Road
·         Completed storm sewer installation
·         Begin testing newly installed water main.

Work Anticipated to be performed, June 12th to June 16th  
·         Perform necessary testing and acquiring needed approvals prior to placing the new water main into service

Starting the week of June 19th, the contractor will begin installing new water services to each home for connection by the homeowner at a future date. We will attempt to contact you to determine the best place for the water service to make it easiest for future connections. If you do have a preferred location, please contact us to schedule a time to meet.

 

Thanks again for all your patience and understanding during construction.

Friday, June 2, 2017

Storm Sewer Continues

Work Completed, May 30th to June 2nd  
·         Storm sewer installation on-going.

Work Anticipated to be performed, June 5th to June 9th
·         Complete water main installation across Wagner Road
·         Continue with Storm Sewer installation

Thanks again for all your patience during construction.